WTP Mechanical, Electrical & Instrumentation Installation
- Fabrication
- Patagonia, Arizona
Water Treatment Plant Installation / Mine Infrastructure
The project installed a mine-site water treatment plant, including FRP/HDPE tanks, a lime silo, multi-flow unit, filter press, pumps, steel platforms, stairs, and handrails. Work included process piping, electrical and instrumentation connections, and commissioning support, all delivered under an accelerated schedule.
Project Details
- Owner Type
- Mining Company
- Primary Scope
- Process Piping · Utilities · Water Treatment / Mechanical
About the Project
Meridian installed the major mechanical components required to bring a mine-site water-treatment plant into operation, including FRP/HDPE tanks, a lime silo, multi-flow unit, filter press, pumps, steel platforms, stairs, and handrails. The team also connected process piping, electrical systems, and instrumentation between the components and supported startup and commissioning.
The work was delivered under an accelerated schedule that required extended shifts and seven-day workweeks. Meridian self-performed the process-piping and steel-platform installation scopes, maintaining direct control over critical field execution.
More Work
Related Projects
-
Mining and Industrial
Mine Facility Expansion
-
Pima County, AZ · Mining and Industrial
Booster and Pipe Construction
-
Green Valley, Pima County, AZ · Mining and Industrial
AZ Mining Booster Station
-
Bayard, New Mexico · Mining and Industrial
PLS Pipeline Reroute
-
Lower Greasewood / Ganado, Navajo Nation, Arizona · Mining and Industrial
Lower Greasewood Water System: Industrial Project
-
Chino, NM · Mining and Industrial
Flood Pipeline Reroute
1 – 3 of 6