Replacement of American Canal Lining
- Federal Civil
- El Paso County, Texas
Canal Rehabilitation / Environmental Remediation
Meridian reconstructed 2,600 LF of the American Canal for the IBWC, placing approximately 5,800 CY of structural concrete and 1.03 million pounds of reinforcing steel while removing 17,000 CY of contaminated soil. The scope also included in-house fabrication and installation of a new pedestrian bridge.
Project Details
- Owner Type
- Federal Agency
- Primary Scope
- Box Culvert · Drainage / Flood Control · Earthwork / Grading · Structural Concrete · Utilities
About the Project
Meridian reconstructed 2,600 LF of the American Canal for the International Boundary and Water Commission, removing the existing lining and building new trapezoidal and U-channel concrete sections, closed box culverts, storm-drain inlets, transition structures, and a Replogle flume. The work combined heavy civil construction with groundwater control and contaminated-soil remediation in an environmentally sensitive corridor.
The project included approximately 5,800 CY of structural concrete, 1.03 million pounds of reinforcing steel, and excavation and disposal of 17,000 CY of impacted soil. Meridian also rehabilitated existing structures and fabricated and installed a new pedestrian bridge and trash rack, self-performing 78% of the contract scope.
More Work
Related Projects
-
Mining and Industrial
Mine Facility Expansion
-
Pima County, AZ · Mining and Industrial
Booster and Pipe Construction
-
Green Valley, Pima County, AZ · Mining and Industrial
AZ Mining Booster Station
-
Patagonia, Arizona · Fabrication
WTP Mechanical, Electrical & Instrumentation Installation
-
Tohono O’odham Nation, Arizona · Federal Civil
High-Water Crossing at Vamori Wash
-
Bernalillo County, New Mexico · DOT / Transportation
Tramway Boulevard (NM 556) Bridge Rehabilitation
1 – 3 of 6